Rapid progress continues to be made on site and with 6 weeks until Christmas shutdown the builder is well placed for an early completion. Since our last report,  we can advise all frame work and rough in works (hydraulic, fire services, electrical and plumbing) are completed throughout. Furthermore the associated plaster works are now well advanced.

As we compile this month’s edition, plaster works are completed to L1 and L2, while L3 has commenced and delivery of L4 is due in the coming weeks. At this stage of the project, the painters and tilers have made a big impression to L1. All apartment ceilings have been completed with three coats of paint, while all the walls have had a base coat sealer and first coat applied finish.

Floor and wall tiling is underway to all bathrooms and kitchens on L1, while kitchen joinery is arriving on site with installation under way. It is also expected that in the coming weeks glass splashbacks and stone bench tops will arrive for L1 and L2 and we also expect to see electrical fit-off of lights and power points commence to L1.

The upper levels will follow program accordingly and it is advised that by Christmas shutdown all plastering works through the hallways and units will be completed, L1 will be well advanced and nearing completion with the painters, tilers, and joinery supply making inroads on the upper levels

Completion: July 2013